How Long Do Projects Take?

Building in Danville, Alamo & Pleasanton Timelines?

  • Kitchen - Basic (4 to 10 Weeks) High-End/Structural (12 to 16+ Weeks)

  • Bathroom - Guest Bathroom (4 to 6 Weeks) Primary Bathroom (6 to 10 Weeks)

  • Whole House Remodel - Light Remodel (3 to 4 Months) Major Remodel (4 to 8+ Months)

  • Additions - 200 to 800 SF (4 to 8+ Months)

  • ADUs - 600 to 1,400 SF (6 to 8+ Months)

    *Please note that these timeline(s) are subject to change based on Site Conditions, Material Selections, Structural Modifications, Permit Requirements, Age of Home, etc.

✳︎